Project KickOff

Information has been changed for confidentiality reasons 

Meet the Team

Project Overview

Project Milestones

Project Costs

Agenda

Communication Plan

What We Need From You

Next Steps

  • Project Planning and Oversight

  • Team Coordination

  • Budget Management

  • Issue Resolution

  • Technical planning for store installations

  • Implementation of Upgrades

  • Training for Customers

  • Creation of Dashboards 

Meet the Team!

Natalie Bailey

John Doe

Jane Doe

Project Manager

Installation Manager

Support Manager

Project Overview

01

02

03

04

05

06

Store

Store

Store

Store

Store

Store

  • Add 80 sensor shelves

  • Add 6 cameras

  • Add Second entrance turnstile

  • Upgrade Network Rack

  • Add 80 sensor shelves

  • Add 6 cameras

  • Add Second entrance turnstile

  • Upgrade Network Rack

  • Add 30 sensor shelves

  • Add 4 cameras

  • Add Second entrance turnstile

  • Upgrade Network Rack

  • Upgrade 120 sensor shelves

  • Add 2 cameras

  • Add Second entrance turnstile

  • Upgrade Network Rack

  • Swap out broken camera

  • Upgrade 90 sensor shelves

  • Upgrade 90 sensor shelves

Communication Plan

Description

Frequency

Channel

Stakeholders

Owner

Project Check-in

Daily

Slack

All Project

Project Team

Project Status Updates

Virtual Project Team Meetings

External Stakeholder updates

Milestone and Deliverables update

Weekly

Bi-weekly

Bi-weekly

As Needed

Email

Google Meet

Google Meet

Google Meet

All internal stakeholders and project team

All project team members

Project managers and contractors

Project Team

Project Manager

Project Manager

Support Manager

All project team members

Milestones and Timeline

June

July

August

September

Go on site to gather store measurements

Update Store Maps for turnstiles and cameras

Update Shelf Planogram

Order Equipment

Add firmware and name to devices

Update Dashboard

Install Turnstiles

Remove old sensor shelves

Install QR Scanners, Cameras, and Shelves

Label all devices and shelves

Update Switch Port Maps

Camera Orientation and Calibration

Calibrate Shelves

Store Testing

May

Project Costs

Onsite Launch Support

Equipment

$100,125

Training & Support

$6,000

Installation

$14,500

Turnstiles

Cameras

Sensor Shelves

Contract Labor

Onsite Installation Services

Setup Services

Training

Total Costs

$120,625

19

490

4

1 day

2 Techs

20 days

03

Any conflicting events between the 2 football games

What We Need From You

01

Outlet maps for the stores

02

- Electrical Schedule

- Construction Schedule

Next Steps

Verify Updated Store Maps and Shelf Planograms

Confirm Equipment Order 

Confirm Installation Dates